We offer you the complete performance for the building of a base plate. In the following, we will show you what is included in our performance and how a Schwedenplatte foundation is built.

After the taking-off of the mothersoil, the laying of all lines and pipes and the applying of the frost-preventing layer, the edge elements are laid. Their exterior shield is surface-ready.

After the construction of the gravel bed and the laying of empty conduits for media (telephone, gas, electricity etc.) and the waste-water pipes the gravel bed is solidified (capillary-breaking layer). Then follows the fine levelling and the laying of the edge elements.

Now the EPS-plates are laid in 2 layers overlapping (each layer 100 mm respectively). Then the recesses for load-bearing wall constructions are measured in.

On the second insulation layer now according to plan all heating coils of the floor heating as well as cold and hot water pipes are laid.

The first layer consists of XPSN-V-L plates, upon which later the load-bearing walls will stand. Between the first and the second layer of the altogether 200-mm thick insulation, PE foil will be inserted.

laying of cold and hot water pipes in PE pipes as well as the heating coils (per room one separate circuit). Laying of reinforcement according to the statician’s circuit diagram.

Then follows the reinforcement according to statics. Then the pouring of the concrete plate can begin. In doing so, the edge and shell elements determine the measure of height.

The concreting process is checked by means of laser technique. (C25/30er Korn (according to statics).

After a drying period of 3–5 hours, the flattening can be done with a power trowel. 3 days later, the shell construction can be started. Under bad weather conditions, the surface is taken off with a hand trowel. After the hardening of the concrete, the surface is completely ready for tiles, carpeting or parquet.

follow-up flattening with a power trowel.

Glossary

Capillary-breaking layer
this layer is for the understructure of base plates. It prevents the damming-up of water.
EPS-plates
warmth-insulating plates for insulation under the base plate.
Formwork plan
Dies ist der Plan für die Armierung im Beton, erstellt und berechnet vom Statiker.
Reinforcement